Georgia

For Georgia, preliminary notice required is conditional — not required for GC; required for subs/remote claimants not in privity with GC only if a Notice of Commencement was filed; notice name is Notice to Contractor; notice deadline — gc (days) is not required; notice deadline — sub/supplier (days) is 30; lien recording deadline — gc (days) is 90, recorded from its source on 2026-08-14.

State
Georgia
Preliminary notice required
conditional — not required for GC; required for subs/remote claimants not in privity with GC only if a Notice of Commencement was filed our reading
Notice name
Notice to Contractor verified
Notice deadline — GC (days)
not required verified
Notice deadline — sub/supplier (days)
30 verified
Lien recording deadline — GC (days)
90
Lien recording deadline — sub/supplier (days)
90
Enforcement deadline (days)
365
Late notice consequence
forfeiture our reading
Statute
O.C.G.A. §44-14-360 et seq.
Sourcemechanicslien.com
Verified
Review by
DatasetMechanics lien filing deadlines, preliminary notice requirements, and enforcement windows by US state and party role

Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.

What the source says

Serve the Notice to Contractor on the prime contractor within 30 days of first furnishing labor or materials, OR within 30 days after the filing of the Notice of Commencement, whichever date is later. If Notice of Commencement is not filed, Notice to Contractor is not required.

mechanicslien.com, retrieved 2026-08-14