Colorado
For Colorado, preliminary notice required is conditional — no pre-work notice required; Notice of Intent to File Lien Statement must be served at least 10 days before recording for all claimants; notice name is Notice of Intent to File Lien Statement; notice deadline — gc (days) is not required; notice deadline — sub/supplier (days) is 10 days before filing; lien recording deadline — gc (days) is 4 months, recorded from its source on 2026-08-14.
- State
- Colorado
- Preliminary notice required
- conditional — no pre-work notice required; Notice of Intent to File Lien Statement must be served at least 10 days before recording for all claimants our reading
- Notice name
- Notice of Intent to File Lien Statement verified
- Notice deadline — GC (days)
- not required
- Notice deadline — sub/supplier (days)
- 10 days before filing
- Lien recording deadline — GC (days)
- 4 months
- Lien recording deadline — sub/supplier (days)
- 4 months
- Enforcement deadline (days)
- 6 months
- Late notice consequence
- forfeiture our reading
- Statute
- C.R.S. §38-22-101 et seq.
Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.
What the source says
No pre-work preliminary notice is required for a prime contractor in privity with the owner. A Notice of Intent to File Lien Statement must still be served on the owner and the prime contractor at least 10 full days before recording the Lien Statement.
— mechanicslien.com, retrieved 2026-08-14
Source
- mechanicslien.comhttps://mechanicslien.com/colorado