For Arkansas, preliminary notice required is conditional — residential GC must deliver Pre-Construction Notice to Owner before commencing work; commercial subs/suppliers must serve Notice to Owner and Contractor within 75 days after last furnishing; all claimants must serve Notice of Intent to Lien at least 10 days before filing; notice name is Notice of Intent to Lien; notice deadline — gc (days) is 10 days before filing lien (Notice of Intent to Lien); before work begins for residential (Pre-Construction Notice); notice deadline — sub/supplier (days) is 75; lien recording deadline — gc (days) is 120, recorded from its source on 2026-08-14.

State
Arkansas
Preliminary notice required
conditional — residential GC must deliver Pre-Construction Notice to Owner before commencing work; commercial subs/suppliers must serve Notice to Owner and Contractor within 75 days after last furnishing; all claimants must serve Notice of Intent to Lien at least 10 days before filing our reading
Notice name
Notice of Intent to Lien verified
Notice deadline — GC (days)
10 days before filing lien (Notice of Intent to Lien); before work begins for residential (Pre-Construction Notice)
Notice deadline — sub/supplier (days)
75 verified
Lien recording deadline — GC (days)
120
Lien recording deadline — sub/supplier (days)
120
Enforcement deadline (days)
15 months
Late notice consequence
forfeiture our reading
Statute
AR Code Ann. §18-44-101 et seq.
Sourcemechanicslien.com
Verified
Review by
DatasetMechanics lien filing deadlines, preliminary notice requirements, and enforcement windows by US state and party role

Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.

What the source says

On commercial projects, subcontractors and material suppliers must serve a Notice to Owner and Contractor within 75 days after last furnishing labor or materials. Every claimant must also serve a Notice of Intent to Lien on the owner at least 10 days before filing the lien.

mechanicslien.com, retrieved 2026-08-14