Delaware
For Delaware, owner-to-gc payment deadline (days) is 30; gc-to-sub flow-down deadline (days) is 15; late-payment interest rate is 5% over Federal Reserve discount rate per year; project types covered is both; attorney fees recoverable is yes, verified against its source on 2026-08-15.
- State
- Delaware verified
- Owner-to-GC payment deadline (days)
- 30 verified
- GC-to-sub flow-down deadline (days)
- 15 verified
- Late-payment interest rate
- 5% over Federal Reserve discount rate per year verified
- Project types covered
- both verified
- Attorney fees recoverable
- yes verified
- Statutory citation
- Del. Code Title 6, §§3501 et seq. and §2301 (private); Del. Code Title 29, §6516(f) (public) verified
What the source says
Projects Covered by Prompt Payment in Delaware The state of Delaware regulates prompt payment on both private and public construction projects. Private Projects Payment on private construction projects in Delaware are governed by <https://www.levelset.com/prompt-payment/delaware-prompt-payment-faqs/#faq-item-2301-legal-rate-loans-insured-by-federal-housing-administration> Del. Code. Title 6, §§3501 et seq. and §2301 . These regulations apply to all private construction projects except residential projects of 6 or fewer units. Payment Deadlines for Private Projects Payments from the property owner to prime contractors must be made within 30 days of either the receipt of a request for payment, or the end of the billing period; whichever is later. Once the contractor has received payment, they must in turn pay their subcontractors or suppliers within 15 days.
— levelset.com, retrieved 2026-08-15