Connecticut
For Connecticut, owner-to-gc payment deadline (days) is 30; gc-to-sub flow-down deadline (days) is 25; late-payment interest rate is 1% per month; project types covered is both; attorney fees recoverable is discretionary, verified against its source on 2026-08-15.
- State
- Connecticut verified
- Owner-to-GC payment deadline (days)
- 30 verified
- GC-to-sub flow-down deadline (days)
- 25 verified
- Late-payment interest rate
- 1% per month verified
- Project types covered
- both verified
- Attorney fees recoverable
- discretionary verified
- Statutory citation
- Conn. Gen. Stat. §§42-158i–42-158j (private); Conn. Gen. Stat. §§4a-71–4a-75 and 49-41c (public) verified
What the source says
Projects Covered by Connecticut Prompt Payment Statutes The state of Connecticut regulates prompt payment on both private and public construction projects. Private Projects Private projects in Connecticut are governed by <https://www.cga.ct.gov/current/pub/chap_742b.htm> Conn. Gen. Stat. §§42-158i – 42-158j . These statutes regulate payment on all private construction projects in Connecticut, except: Projects funded by US Department of Housing and Urban Development Prime contracts of $25,000 or less Any residential projects containing 4 or less units Payment Deadlines for Private Projects On qualifying private projects in Connecticut, the property owner must pay the prime contractor within 30 days of invoice receipt. Upon receipt of payment, the prime contractor has 30 days to make payment to their subs and suppliers. In turn, subcontractors must pay their subs or suppliers within 25 days of receipt of payment. Penalties for Late Payment on Private Projects Under Connecticut’s prompt pay laws for private projects, the interest rate on late payments is 1% per month until the balance is paid.
— levelset.com, retrieved 2026-08-15