Building Framing Inspection
For Building Framing Inspection, process is Residential building inspection sequence; jurisdiction is Mecklenburg County, North Carolina; order is 6; what must already be done is after the roof wall, ceiling, and floor framing is complete with appropriate blocking, bracing and fire stopping in place; what may not proceed until it passes is All lintels required to be bolted to the framing for support shall not be covered by any interior or exterior wall or ceiling finish materials before approval, recorded from its source on 2026-08-11.
- Step
- Building Framing Inspection verified
- Process
- Residential building inspection sequence our reading
- Jurisdiction
- Mecklenburg County, North Carolina our reading
- Order
- 6 verified
- What must already be done
- after the roof wall, ceiling, and floor framing is complete with appropriate blocking, bracing and fire stopping in place verified
- What may not proceed until it passes
- All lintels required to be bolted to the framing for support shall not be covered by any interior or exterior wall or ceiling finish materials before approval verified
Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.
What the source says
6. Building Framing Inspection To be made after the roof wall, ceiling, and floor framing is complete with appropriate blocking, bracing and fire stopping in place. The following items should be in place and visible for inspection: Pipes Chimneys and vents Flashing for roofs, chimneys and wall openings Insulation baffles All lintels required to be bolted to the framing for support shall not be covered by any interior or exterior wall or ceiling finish materials before approval.
— code.mecknc.gov, retrieved 2026-08-11