For Foundation Inspection, process is Residential building inspection sequence; jurisdiction is Creve Coeur, Missouri; order is 2; what must already be done is after the top of the footing has been cleaned, the foundation forms have been properly set, the reinforcing steel has been cleaned and tied in place and the proper anchor bolts are on-site; what may not proceed until it passes is No concrete may be placed without this inspection being approved, recorded from its source on 2026-08-11.
- Step
- Foundation Inspection verified
- Process
- Residential building inspection sequence our reading
- Jurisdiction
- Creve Coeur, Missouri our reading
- Order
- 2 verified
- What must already be done
- after the top of the footing has been cleaned, the foundation forms have been properly set, the reinforcing steel has been cleaned and tied in place and the proper anchor bolts are on-site verified
- What may not proceed until it passes
- No concrete may be placed without this inspection being approved verified
Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.
What the source says
2. Foundation Inspection A foundation inspection is required after the top of the footing has been cleaned, the foundation forms have been properly set, the reinforcing steel has been cleaned and tied in place and the proper anchor bolts are on-site. A city-approved barrier must be in place around the excavation until backfilling has occurred. No concrete may be placed without this inspection being approved.
— crevecoeurmo.gov, retrieved 2026-08-11
Source
- crevecoeurmo.govhttps://www.crevecoeurmo.gov/86/Sequence-of-Inspections