Duty to Request a Final Inspection and Obtain Final Approval
For Duty to Request a Final Inspection and Obtain Final Approval, process is Residential building inspection sequence; jurisdiction is Creve Coeur, Missouri; order is 10; what must already be done is Upon completion of the work described in the permit application and on the approved construction documents; what may not proceed until it passes is the permit holder must request a final inspection and obtain final approval before any occupancy of the building or structure may occur, recorded from its source on 2026-08-11.
- Step
- Duty to Request a Final Inspection and Obtain Final Approval verified
- Process
- Residential building inspection sequence our reading
- Jurisdiction
- Creve Coeur, Missouri our reading
- Order
- 10 verified
- What must already be done
- Upon completion of the work described in the permit application and on the approved construction documents verified
- What may not proceed until it passes
- the permit holder must request a final inspection and obtain final approval before any occupancy of the building or structure may occur verified
Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.
What the source says
10. Duty to Request a Final Inspection and Obtain Final Approval Upon completion of the work described in the permit application and on the approved construction documents, the permit holder must request a final inspection and obtain final approval before any occupancy of the building or structure may occur. Failure of the permit holder to obtain final approval constitutes a violation of the Building Code and subjects the permit holder to penalties as set forth in Section 116.4.
— crevecoeurmo.gov, retrieved 2026-08-11