Utah

For Utah, owner-to-gc payment deadline (days) is 45; gc-to-sub flow-down deadline (days) is 30; late-payment interest rate is 1% per month; project types covered is both; attorney fees recoverable is yes, verified against its source on 2026-08-15.

State
Utah verified
Owner-to-GC payment deadline (days)
45 verified
GC-to-sub flow-down deadline (days)
30 verified
Late-payment interest rate
1% per month verified
Project types covered
both verified
Attorney fees recoverable
yes verified
Statutory citation
Utah Code §§ 13-8-5 and 58-55-603 verified
Sourcelevelset.com
Verified
Review by
DatasetConstruction prompt payment act deadlines by US state — owner-to-contractor and contractor-to-subcontractor payment windows, retention release deadlines, and late-payment interest rates

What the source says

For final payments, including retainage, the owner must pay the prime within 45 days of receipt of a request for final payment, or the issuance of a certificate of occupancy; whichever is later. Regarding payments to subcontractors, the prime must make progress payments within 30 days after they received payment. Final payments must be made within 10 days of when the prime received payment.

levelset.com, retrieved 2026-08-15