Utah

For Utah, owner-to-gc payment deadline (days) is 45; gc-to-sub flow-down deadline (days) is 30; late-payment interest rate is 1% per month; project types covered is both; attorney fees recoverable is yes, recorded from its source on 2026-08-15; source re-checked 2026-09-29.

State
Utah
Owner-to-GC payment deadline (days)
45 verified
GC-to-sub flow-down deadline (days)
30 verified
Late-payment interest rate
1% per month
Project types covered
both
Attorney fees recoverable
yes our reading
Statutory citation
Utah Code §§ 13-8-5 and 58-55-603
Sourcelevelset.com
Verified
Review by
DatasetConstruction prompt payment act deadlines by US state — owner-to-contractor and contractor-to-subcontractor payment windows, retention release deadlines, and late-payment interest rates

Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.

What the source says

For final payments, including retainage, the owner must pay the prime within 45 days of receipt of a request for final payment, or the issuance of a certificate of occupancy; whichever is later. Regarding payments to subcontractors, the prime must make progress payments within 30 days after they received payment. Final payments must be made within 10 days of when the prime received payment.

— levelset.com, retrieved 2026-08-15