Tennessee

For Tennessee, owner-to-gc payment deadline (days) is 30; gc-to-sub flow-down deadline (days) is 30; retention release deadline (days) is 90; late-payment interest rate is 1.5% per month; project types covered is both, verified against its source on 2026-08-15.

State
Tennessee verified
Owner-to-GC payment deadline (days)
30 verified
GC-to-sub flow-down deadline (days)
30 verified
Retention release deadline (days)
90 verified
Late-payment interest rate
1.5% per month verified
Project types covered
both verified
Attorney fees recoverable
discretionary verified
Statutory citation
Tenn. Code §66-34-101 et seq. verified
Sourcelevelset.com
Verified
Review by
DatasetConstruction prompt payment act deadlines by US state — owner-to-contractor and contractor-to-subcontractor payment windows, retention release deadlines, and late-payment interest rates

What the source says

Once the prime has received payment, all other payments must be made within 30 days of receipt of payment. Penalties for Late Payment on Public Projects Any wrongfully withheld payments will be subject to a 1.5% per month interest rate, accruing the day after payment becomes due. If still unpaid for 60 days, the interest accrued up to that point will be added to the principal amount of the debt, and continue to accrue on the increased amount. Tennessee Prompt Payment Frequently Asked Questions Tennessee's prompt payment requirements are found in two separate statutes: One for private construction projects ( <https://advance.lexis.com/api/document/collection/statutes-legislation/id/4X8K-WKT0-R03M-80BY-00008-00?cite=Tenn.%20Code%20Ann.%20%C2%A7%2066-34-101&context=1000516> Tenn. Code Ann. § 66-34-101 et. seq. ), and one for public construction projects ( <https://advance.lexis.com/api/document/collection/statutes-legislation/id/4X8K-V930-R03K-62HT-00008-00?cite=Tenn.%20Code%20Ann.%20%C2%A7%2012-4-701&context=1000516> Tenn. Code Ann. § 12-4-701 et. seq. ). Below are frequently asked questions about both