Oklahoma

For Oklahoma, owner-to-gc payment deadline (days) is 28; gc-to-sub flow-down deadline (days) is 10; late-payment interest rate is none; project types covered is private; attorney fees recoverable is no, recorded from its source on 2026-08-15; source re-checked 2026-09-29.

State
Oklahoma
Owner-to-GC payment deadline (days)
28 verified
GC-to-sub flow-down deadline (days)
10 verified
Late-payment interest rate
none
Project types covered
private
Attorney fees recoverable
no our reading
Statutory citation
Okla. Stat. Title 15, §820
Sourcelevelset.com
Verified
Review by
DatasetConstruction prompt payment act deadlines by US state — owner-to-contractor and contractor-to-subcontractor payment windows, retention release deadlines, and late-payment interest rates

Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.

What the source says

Payments from the property owner to the prime are due within 28 calendar days after receipt of a request for payment. As for payments to subcontractors and suppliers down the payment chain, payments must be made within 10 days of the higher-tiered party receiving payment.

— levelset.com, retrieved 2026-08-15