For Nebraska, owner-to-gc payment deadline (days) is 30; gc-to-sub flow-down deadline (days) is 10; retention release deadline (days) is 45; late-payment interest rate is 1% per month; project types covered is both, verified against its source on 2026-08-15.
- State
- Nebraska verified
- Owner-to-GC payment deadline (days)
- 30 verified
- GC-to-sub flow-down deadline (days)
- 10 verified
- Retention release deadline (days)
- 45 verified
- Late-payment interest rate
- 1% per month verified
- Project types covered
- both verified
- Attorney fees recoverable
- discretionary verified
- Statutory citation
- Neb. Rev. Stat. §§ 45-1201 – 45-1210 (private); Neb. Rev. Stat. §§ 81-2401 – 81-2408 (public) verified
What the source says
30 days after payment request. Retainage must be released within 45 days of the project's substantial completion. 10 DAYS Subcontractors General contractors in Nebraska must pay subcontractors within 10 days after receiving payment. This deadline applies to retainage payments as well. 10 DAYS Suppliers Payment is due to material suppliers on private projects within 10 days after the hiring party receives payment. 1% / MONTH Interest & Fees Nebraska's Prompt Payment Act for private construction projects charges interest of 1% per month on late payments. 45 DAYS Prime Contractors Public agencies in Nebraska must pay the Prime Contractor within 45 days after either receipt of an invoice or receipt of services, whichever is later. NO DAYS Subcontractors On public construction projects, payments to subcontractors are not regulated by Nebraska statute. NO DAYS Suppliers On public construction projects, payments to suppliers are not regulated by Nebraska statute. YES Interest & Fees Nebraska's Prompt Payment Act for public projects sets the interest penalty equal to "the average short-term borrowing rate for the federal government during July of the previous year rounded to the nearest whole percentage” plus 3%. Choose Different State Alabama Alaska Arizona Arkansas California Colorado Connecticut Delaware Florida Georgia Hawaii Idaho Illinois Indiana Iowa Kansas Kentucky Louisiana Maine Maryland Massachusetts Michigan Minnesota Mississippi Missouri Montana Nebraska Nevada New Hampshire New Jersey New Mexico New York North Carolina North Dakota Ohio Oklahoma Oregon Pennsylvania Rhode Island South Carolina South Dakota Tennessee Texas Utah Vermont Virginia Washington DC Washington West Virginia Wisconsin Wyoming Choose Different Nebraska Topic Preliminary Notice Mechanics Lien Bond Claim Lien Waiver Prompt Payment Retainage Skip down to FAQs Prompt payment laws in Nebraska set a deadline for payments on both public and private construction projects.
— levelset.com, retrieved 2026-08-15
Source
- levelset.comhttps://www.levelset.com/prompt-payment/nebraska-prompt-payment-faqs/