For Louisiana, gc-to-sub flow-down deadline (days) is 14; late-payment interest rate is 0.5% per day, up to 15% maximum; project types covered is both; attorney fees recoverable is yes; statutory citation is La. Rev. Stat. §9:2784, recorded from its source on 2026-08-15; source re-checked 2026-09-29.

State
Louisiana
GC-to-sub flow-down deadline (days)
14
Late-payment interest rate
0.5% per day, up to 15% maximum
Project types covered
both
Attorney fees recoverable
yes our reading
Statutory citation
La. Rev. Stat. §9:2784
Sourcelevelset.com
Verified
Review by
DatasetConstruction prompt payment act deadlines by US state — owner-to-contractor and contractor-to-subcontractor payment windows, retention release deadlines, and late-payment interest rates

Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.

What the source says

If the contractor or subcontractor without reasonable cause fails to make any payment to his subcontractors and suppliers within fourteen consecutive days of the receipt of payment from the owner for improvements to an immovable, the contractor or subcontractor shall pay to the subcontractors and suppliers, in addition to the payment, a penalty in the amount of one-half of one percent of the amount due, per day, from the expiration of the period allowed herein for payment after the receipt of payment from the owner. The total penalty shall not exceed fifteen percent of the outstanding balance due.

— levelset.com, retrieved 2026-08-15