For Georgia, owner-to-gc payment deadline (days) is 15; gc-to-sub flow-down deadline (days) is 10; late-payment interest rate is 1% per month; project types covered is both; attorney fees recoverable is yes, verified against its source on 2026-08-15.

State
Georgia verified
Owner-to-GC payment deadline (days)
15 verified
GC-to-sub flow-down deadline (days)
10 verified
Late-payment interest rate
1% per month verified
Project types covered
both verified
Attorney fees recoverable
yes verified
Statutory citation
O.C.G.A. §§13-11-1 to 13-11-11 verified
Sourcelevelset.com
Verified
Review by
DatasetConstruction prompt payment act deadlines by US state — owner-to-contractor and contractor-to-subcontractor payment windows, retention release deadlines, and late-payment interest rates

What the source says

In Georgia, the same set of prompt payment rules apply to both public and private construction jobs. These statutes can be found in <https://www.levelset.com/prompt-payment/georgia-prompt-payment-faqs/#faq-item-13111-title> O.C.G.A. §§13-11-1 to 13-11-11 . These timeframes apply to almost every construction project in Georgia, with two notable exceptions. In the residential projects world, these regulations don’t apply to residential projects of 12 units or fewer As for public projects, the prompt pay deadlines won’t apply in counties of less than 10,000 people, or towns with a population of less than 2,500. Once a contractor has satisfied the conditions of their contract, they are entitled to payment. A proper invoice, submitted to the owner according to the contract payment terms, will start the clock on the payment deadline. Upon receipt, the owner will have 15 days to release payment to the prime contractor.

levelset.com, retrieved 2026-08-15

Source

Last verified against source: . Due for re-check by . This page as Markdown · OKF bundle · full dataset as JSON.