Reference Source

California

For California, owner-to-gc payment deadline (days) is 30; gc-to-sub flow-down deadline (days) is 7; late-payment interest rate is 2% per month; project types covered is both; attorney fees recoverable is yes, recorded from its source on 2026-08-14; source re-checked 2026-09-29.

State
California verified
Owner-to-GC payment deadline (days)
30 verified
GC-to-sub flow-down deadline (days)
7
Late-payment interest rate
2% per month verified
Project types covered
both
Attorney fees recoverable
yes our reading
Statutory citation
Cal. Civ. Code 8800; Cal. Pub. Cont. Code 10261.5, 20104.50 verified
Sourcemechanicslien.com
Verified
Review by
DatasetConstruction prompt payment act deadlines by US state — owner-to-contractor and contractor-to-subcontractor payment windows, retention release deadlines, and late-payment interest rates

Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.

What the source says

The California Prompt Payment Act forces public and private project owners to pay contractors within 30 days of receiving an undisputed invoice (Cal. Civ. Code 8800; Cal. Pub. Cont. Code 10261.5, 20104.50). Late payments accrue 2% per month interest plus attorney's fees for the prevailing party.

— mechanicslien.com, retrieved 2026-08-14