Reference Source

San Diego County

For San Diego County, source type is department page; permit type is building permit; deadline to start work is it will expire if the work is not started within two years. To meet this requirement, the permittee must call for, and pass a valid inspection; inactivity window is passing a valid inspection at least every 180 days (six months); maximum permit life is all work must be completed within three years, recorded from its source on 2026-08-11.

Jurisdiction
San Diego County verified
Source type
department page our reading
Permit type
building permit our reading
Deadline to start work
it will expire if the work is not started within two years. To meet this requirement, the permittee must call for, and pass a valid inspection verified
Inactivity window
passing a valid inspection at least every 180 days (six months) verified
Maximum permit life
all work must be completed within three years verified
Renewal fee basis
One-half of current permit fees are due upon renewal unless progress has been made (and approved) so that only a final inspection is needed, then one-quarter of current permit fees are due verified
Code citation
Sec. 91.1.105.5.2 verified
Sourcesandiegocounty.gov
Verified
Review by
DatasetBuilding permit expiry, progress and renewal rules by jurisdiction

Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.

What the source says

San Diego County's Building Code sets timeline requirements when building permits are issued. The work authorized by the permit must begin and demonstrate progress by certain dates, and all work must be completed within three years. From the day the permit is issued, it will expire if the work is not started within two years. To meet this requirement, the permittee must call for, and pass a valid inspection. If no inspection has been scheduled and passed within the first two years, the permit becomes null and void. Once the work has started and the first required inspection has been passed, the permittee must show that the work is progressing by passing a valid inspection at least every 180 days (six months). If these progress requirements are not met the permit will expire. This applies regardless of when the first inspection took place within the first two years of the life of the permit. To renew an expired building permit that has received and passed at least one valid inspection, but has not exceeded the three-year mark: The plans cannot be changed, nor changes proposed. One-half of current permit fees are due upon renewal unless progress has been made (and approved) so that only a final inspection is needed, then one-quarter of current permit fees are due. ( Sec. 91.1.105.5.2 of the

sandiegocounty.gov, retrieved 2026-08-11

Source

Last verified against source: . Due for re-check by . This page as Markdown · OKF bundle · full dataset as JSON.