# North Dakota — Mechanics lien filing deadlines, preliminary notice requirements, and enforcement windows by US state and party role For North Dakota, preliminary notice required is yes — all claimants must serve Notice of Intention to Claim a Construction Lien on owner at least 10 days before filing; notice name is Notice of Intention to Claim a Construction Lien; notice deadline — gc (days) is 10 days before filing; notice deadline — sub/supplier (days) is 10 days before filing; lien recording deadline — gc (days) is 90, recorded from its source on 2026-08-14. - **State:** North Dakota _(verified: appears in the quote below)_ - **Preliminary notice required:** yes — all claimants must serve Notice of Intention to Claim a Construction Lien on owner at least 10 days before filing _(our reading, not quoted from the source)_ - **Notice name:** Notice of Intention to Claim a Construction Lien _(verified: appears in the quote below)_ - **Notice deadline — GC (days):** 10 days before filing _(verified: appears in the quote below)_ - **Notice deadline — sub/supplier (days):** 10 days before filing _(verified: appears in the quote below)_ - **Lien recording deadline — GC (days):** 90 _(verified: appears in the quote below)_ - **Lien recording deadline — sub/supplier (days):** 90 _(verified: appears in the quote below)_ - **Enforcement deadline (days):** 1095 - **Late notice consequence:** forfeiture _(our reading, not quoted from the source)_ - **Statute:** NDCC Chapter 35-27 _(verified: appears in the quote below)_ ## What the source says > NDCC Chapter 35-27 — Private Works, Payment Bonds & Public Projects Create Your Account File a Claim Call (800) 432-7799 Free ND Deadline Calculator Calculate your North Dakota deadlines and get a free consultation. North Dakota mechanic lien deadline table with toggles for project type and claimant type. North Dakota Preliminary Notice & Mechanic Lien Deadlines Select your project type and role to see the deadlines that apply to you. Project Type Private Projects Public Works Select Your Tier Prime Contractor Subcontractors & Suppliers Remote Claimants Prime Contractor — In privity with the property owner Preliminary Notice Mechanic Lien Enforcement 10 days before filing Serve the Notice of Intention to Claim a Construction Lien on the owner at least 10 days before filing the Construction Lien. Required for all claimants, including prime contractors in privity with the owner. If the owner demands a statement of account, wait an additional 10 days after providing the statement before filing. Send Preliminary Notice 90 ## Source - https://mechanicslien.com/north-dakota Last verified: 2026-08-14. Review by: 2027-08-14. Part of [Mechanics lien filing deadlines, preliminary notice requirements, and enforcement windows by US state and party role](https://referencesource.org/mechanics-lien-deadlines-by-state/).