# Wisconsin — Construction prompt payment act deadlines by US state — owner-to-contractor and contractor-to-subcontractor payment windows, retention release deadlines, and late-payment interest rates For Wisconsin, owner-to-gc payment deadline (days) is 30; gc-to-sub flow-down deadline (days) is 7; late-payment interest rate is 1% per month; project types covered is public; attorney fees recoverable is yes, verified against its source on 2026-08-15. - **State:** Wisconsin _(verified: appears in the quote below)_ - **Owner-to-GC payment deadline (days):** 30 _(verified: appears in the quote below)_ - **GC-to-sub flow-down deadline (days):** 7 _(verified: appears in the quote below)_ - **Late-payment interest rate:** 1% per month _(verified: appears in the quote below)_ - **Project types covered:** public _(verified: appears in the quote below)_ - **Attorney fees recoverable:** yes _(verified: appears in the quote below)_ - **Statutory citation:** Wis. Stat. §§ 16.528, 16.53(2) and 66.0135 _(verified: appears in the quote below)_ ## What the source says > Wisconsin does not provide a prompt payment for private projects. ## Source - https://www.levelset.com/prompt-payment/wisconsin-prompt-payment-faqs/ Last verified: 2026-08-15. Review by: 2027-08-15. Part of [Construction prompt payment act deadlines by US state — owner-to-contractor and contractor-to-subcontractor payment windows, retention release deadlines, and late-payment interest rates](https://referencesource.org/construction-prompt-payment-deadlines-by-state/).