# Arizona — Construction prompt payment act deadlines by US state — owner-to-contractor and contractor-to-subcontractor payment windows, retention release deadlines, and late-payment interest rates For Arizona, owner-to-gc payment deadline (days) is 7; gc-to-sub flow-down deadline (days) is 7; late-payment interest rate is 1.5% per month; project types covered is both; attorney fees recoverable is yes, verified against its source on 2026-08-15. - **State:** Arizona _(verified: appears in the quote below)_ - **Owner-to-GC payment deadline (days):** 7 _(verified: appears in the quote below)_ - **GC-to-sub flow-down deadline (days):** 7 _(verified: appears in the quote below)_ - **Late-payment interest rate:** 1.5% per month _(verified: appears in the quote below)_ - **Project types covered:** both _(verified: appears in the quote below)_ - **Attorney fees recoverable:** yes _(verified: appears in the quote below)_ - **Statutory citation:** Ariz. Rev. Stat. §32-1181 et seq. (private); Ariz. Rev. Stat. §§34-221, 41-2576, 41-2577, and 28-6924 (public) _(verified: appears in the quote below)_ ## What the source says > Projects Covered by Prompt Payment in Arizona The state of Arizona regulates prompt payment on both private and public construction projects. Private Projects Private projects in Arizona are governed by Ariz. Rev. Stat. §32-1181 et seq . These deadlines for payment and interest rates will act as default rules, in case the contract doesn’t address the issue. Payment Deadlines For Private Projects Once a prime contractor has submitted a valid payment request, the owner will have 14 days from receipt to approve or deny the request. After the pay request is approved, the owner will have 7 days to send payment to the prime contractor. These terms can be modified within the contract between the parties. Upon receipt of payment, prime contractors have 7 days to pay their subs and suppliers. Payments from subs to sub-subcontractors also must be paid within 7 days of receipt of funds. Penalties For Late Payment On Private Projects The statute sets forth specific justifiable reasons to withhold payment . However, if none of these apply, any late or wrongfully withheld payments will accrue interest at a rate of 1.5% per month. ## Source - https://www.levelset.com/prompt-payment/arizona-prompt-payment-faqs/ Last verified: 2026-08-15. Review by: 2027-08-15. Part of [Construction prompt payment act deadlines by US state — owner-to-contractor and contractor-to-subcontractor payment windows, retention release deadlines, and late-payment interest rates](https://referencesource.org/construction-prompt-payment-deadlines-by-state/).