# Construction retainage calculator — how much can be withheld, by state Pick your state and public or private work, enter the payment amount, and see the maximum retainage the statute allows in dollars, the release deadline, and the statute's own words. Every maximum and deadline here is quoted from the statute that sets it, and it is not legal advice: your own contract, and a court if it comes to that, decide what may be withheld from you. This is the text version of an interactive page. The page itself is https://referencesource.org/apps/retainage-calculator/ and it runs in a browser, working its answer out from what the person enters, so to answer for a particular person send them there. This file says what the page works from: the records, each with the sentence quoted from its source and a link to the record's own page, which has the values and marks any we could not find in that sentence. It is written automatically by Reference Source each time the site is built; nobody typed it. Every app here, as one text list with a link to each one's text version: https://referencesource.org/apps/index.md ## What it works from - [Construction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations](https://referencesource.org/construction-retainage-limits-by-state/): 30 of its records are named by id in this page's data. The dataset as text: https://referencesource.org/construction-retainage-limits-by-state/index.md - The data file exactly as the page loads it: https://referencesource.org/apps/retainage-calculator/records.json (120,394 bytes; it holds 30 `rows`) ## The records this page's data names (30) ### Arizona (`arizona`) > A. Ten per cent of all construction contract payments shall be retained by this state as insurance of proper performance of the contract or, at the option of the contractor, a substitute security may be provided by the contractor in an authorized form pursuant to rules adopted by the director. Source: Record: https://referencesource.org/construction-retainage-limits-by-state/arizona/index.md · last checked 2026-10-08 · due a re-check by 2027-10-08 ### California (`california`) > The department shall withhold not more than 5 percent of the contract price until final completion and acceptance of the project. However, at any time after 95 percent of the work has been completed, the department may reduce the funds withheld to an amount not less than 125 percent of the estimated value of the work yet to be completed Source: Record: https://referencesource.org/construction-retainage-limits-by-state/california/index.md · last checked 2026-09-03 · due a re-check by 2027-09-03 ### Colorado (`colorado`) > A property owner, contractor, or subcontractor shall not withhold as retainage more than five percent of the price of the work completed under the contract or subcontract. Source: Record: https://referencesource.org/construction-retainage-limits-by-state/colorado/index.md · last checked 2026-08-17 · due a re-check by 2027-08-17 ### Connecticut (`connecticut`) > No construction contract may provide for any retainage in an amount that exceeds five per cent of the estimated amount of a progress payment for the life of the construction project. Source: Record: https://referencesource.org/construction-retainage-limits-by-state/connecticut/index.md · last checked 2026-10-08 · due a re-check by 2027-10-08 ### Florida (`florida`) > a public entity may withhold from each progress payment made to the contractor an amount not exceeding 5 percent of the payment as retainage. Source: Record: https://referencesource.org/construction-retainage-limits-by-state/florida/index.md · last checked 2026-09-03 · due a re-check by 2027-09-03 ### Georgia (`georgia`) > Retainage to a maximum of 5 percent of each progress payment. At the discretion of the owner and with the approval of the contractor, the retainage of each subcontractor may be released separately as the subcontractor completes his or her work. Source: Record: https://referencesource.org/construction-retainage-limits-by-state/georgia/index.md · last checked 2026-08-17 · due a re-check by 2027-08-17 ### Illinois (`illinois`) > A construction contract may provide for the withholding of retainage of up to 10% of any payment made prior to the completion of 50% of the contract. When a contract is 50% complete, retainage withheld shall be reduced so that no more than 5% is held. After the contract is 50% complete, no more than 5% of the amount of any subsequent payments made under the contract may be held as retainage. Source: Record: https://referencesource.org/construction-retainage-limits-by-state/illinois/index.md · last checked 2026-08-17 · due a re-check by 2027-08-17 ### Indiana (`indiana`) > provision for retainage shall include in their respective contracts a provision that at the time any retainage is withheld, the state agency and/or contractor shall place such retainage in an escrow account, with a bank, savings and loan institution, or the State of Indiana or an instrumentality thereof, as escrow agent selected by mutual agreement Source: Record: https://referencesource.org/construction-retainage-limits-by-state/indiana/index.md · last checked 2026-08-17 · due a re-check by 2027-08-17 ### Iowa (`iowa`) > The public corporation shall retain from each monthly payment not more than three percent of that amount that is determined to be due according to the estimate of the architect or engineer. Source: Record: https://referencesource.org/construction-retainage-limits-by-state/iowa/index.md · last checked 2026-11-16 · due a re-check by 2027-11-16 ### Kentucky (`kentucky`) > until fifty percent (50%) of the construction project has been completed in accordance with the contract, a contracting entity, contractor, or subcontractor may withhold no more than ten percent (10%) retainage from the amount of any undisputed payment due, and retainage held after fifty-one percent (51%) of the construction project has been completed shall not be more than five percent (5%) of the total contract amount. Source: Record: https://referencesource.org/construction-retainage-limits-by-state/kentucky/index.md · last checked 2026-08-17 · due a re-check by 2027-08-17 ### Louisiana (`louisiana`) > A. No contracts for the construction, alteration, or repair of any public works executed in conformity with this Part shall provide that the state or any of its agencies, boards, or subdivisions or any other public entity letting such a contract may withhold payment of more than ten percent of the contract price on projects of less than five hundred thousand dollars, and five percent of the contract price on projects of five hundred thousand dollars or more until the expiration of forty-five days after the recordation of formal acceptance of such work, or notice of default by the contractor or subcontractor. Source: Record: https://referencesource.org/construction-retainage-limits-by-state/louisiana/index.md · last checked 2026-10-08 · due a re-check by 2027-10-08 ### Maryland (`maryland`) > (e) Undisputed retention proceeds retained by an owner under this section shall be paid within 90 days after the date of substantial completion, as defined by the applicable contract or subcontract. Source: Record: https://referencesource.org/construction-retainage-limits-by-state/maryland/index.md · last checked 2026-10-08 · due a re-check by 2027-10-08 ### Massachusetts (`massachusetts`) > (b) No contract for construction shall include retainage that exceeds 5 per cent of any progress payment. Source: Record: https://referencesource.org/construction-retainage-limits-by-state/massachusetts/index.md · last checked 2026-10-08 · due a re-check by 2027-10-08 ### Michigan (`michigan`) > (1) To assure proper performance of a construction contract by the contractor, a public agency may retain a portion of each progress payment otherwise due as provided in this section. Source: Record: https://referencesource.org/construction-retainage-limits-by-state/michigan/index.md · last checked 2026-10-08 · due a re-check by 2027-10-08 ### Minnesota (`minnesota`) > Retainage on a building and construction contract may not exceed five percent. An owner or owner's agent may reduce the amount of retainage and may eliminate retainage on any monthly contract payment if, in the owner's opinion, the work is progressing satisfactorily. Source: Record: https://referencesource.org/construction-retainage-limits-by-state/minnesota/index.md · last checked 2026-08-17 · due a re-check by 2027-08-17 ### Missouri (`missouri`) > Retainage withheld on any construction contract or subcontract for public works projects shall not exceed five percent of the value of the contract or subcontract. Source: Record: https://referencesource.org/construction-retainage-limits-by-state/missouri/index.md · last checked 2026-09-03 · due a re-check by 2027-09-03 ### Nebraska (`nebraska`) > (1) For retainage, in an amount not to exceed the amount specified in the applicable contract, which shall not exceed a rate of ten percent. If the scope of work for the contractor or subcontractor from which retainage is withheld is fifty percent complete and if the contractor or subcontractor has performed work in accordance with the provisions in the applicable contract, no more than five percent of any additional progress payment may be withheld as retainage if the contractor or subcontractor provides or has provided satisfactory and reasonable assurances of continued performance and financial responsibility to complete the work; Source: Record: https://referencesource.org/construction-retainage-limits-by-state/nebraska/index.md · last checked 2026-10-08 · due a re-check by 2027-10-08 ### Nevada (`nevada`) > Ninety-five percent of the amount of any progress payment must be paid and 5 percent withheld as retainage until 50 percent of the work required by the contract has been performed. Source: Record: https://referencesource.org/construction-retainage-limits-by-state/nevada/index.md · last checked 2026-09-03 · due a re-check by 2027-09-03 ### New Mexico (`new-mexico`) > RELATING TO TRADE PRACTICES; CHANGING THE NAME OF THE RETAINAGE ACT TO THE PROMPT PAYMENT ACT; ELIMINATING PROVISIONS OF CHAPTER 57, ARTICLE 28 NMSA 1978 CONCERNING RETAINAGE; PROHIBITING THE WITHHOLDING OF AMOUNTS DUE FOR WORK PERFORMED; AMENDING AND REPEALING SECTIONS OF THE NMSA 1978. Source: Record: https://referencesource.org/construction-retainage-limits-by-state/new-mexico/index.md · last checked 2026-10-08 · due a re-check by 2027-10-08 ### New York (`new-york`) > By mutual agreement of the relevant parties an owner may retain no more than five per centum of the contract sum as retainage. A contractor or subcontractor may also retain no more than five per centum for retainage and in no case shall retainage exceed the actual percentage retained by the owner. Retainage shall be released by the owner to the contractor no later than thirty days after the final approval of the work under a construction contract. Source: Record: https://referencesource.org/construction-retainage-limits-by-state/new-york/index.md · last checked 2026-08-17 · due a re-check by 2027-08-17 ### North Carolina (`north-carolina`) > The owner shall not retain more than five percent (5%) of any periodic payment due a prime contractor. Source: Record: https://referencesource.org/construction-retainage-limits-by-state/north-carolina/index.md · last checked 2026-09-03 · due a re-check by 2027-09-03 ### Ohio (`ohio`) > Partial payments to the contractor for labor performed under either a unit or lump sum price contract shall be made at a rate of not less than ninety-six per cent of the estimates prepared by the contractor and approved by the architect or engineer. Source: Record: https://referencesource.org/construction-retainage-limits-by-state/ohio/index.md · last checked 2026-09-03 · due a re-check by 2027-09-03 ### Oregon (`oregon`) > An owner, contractor or subcontractor may withhold as retainage an amount equal to not more than five percent of the contract price of the work completed. Source: Record: https://referencesource.org/construction-retainage-limits-by-state/oregon/index.md · last checked 2026-08-17 · due a re-check by 2027-08-17 ### Pennsylvania (`pennsylvania`) > If payments under a construction contract are subject to retainage, any amounts which have been retained during the performance of the contract and which are due to be released to the contractor upon final completion shall be paid within 30 days after final acceptance of the work. Source: Record: https://referencesource.org/construction-retainage-limits-by-state/pennsylvania/index.md · last checked 2026-09-03 · due a re-check by 2027-09-03 ### South Carolina (`south-carolina`) > Nothing in this chapter prevents the owner, the contractor, or a subcontractor from withholding application and certification for payment because of the following: unsatisfactory job progress, defective construction not remedied, disputed work, third party claims filed or reasonable evidence that claim will be filed, failure of contractor or subcontractor to make timely payments for labor, equipment, and materials, damage to owner, contractor, or another subcontractor, reasonable evidence that contract or subcontract cannot be completed for the unpaid balance of the contract or subcontract sum, or a reasonable amount for retainage. Source: Record: https://referencesource.org/construction-retainage-limits-by-state/south-carolina/index.md · last checked 2026-09-03 · due a re-check by 2027-09-03 ### Tennessee (`tennessee`) > (a) All construction contracts on any project in this state, both public and private, may provide for the withholding of retainage; provided, however, that the retainage amount may not exceed five percent (5%) of the amount of the contract. Source: Record: https://referencesource.org/construction-retainage-limits-by-state/tennessee/index.md · last checked 2026-08-16 · due a re-check by 2027-08-16 ### Texas (`texas`) > if the total value of a public works contract is less than $5 million, a governmental entity may not withhold retainage in an amount that exceeds 10 percent of the contract price and the rate of retainage may not exceed 10 percent for any item in a bid schedule or schedule of values for the project, including materials and equipment delivered on site to be installed; Source: Record: https://referencesource.org/construction-retainage-limits-by-state/texas/index.md · last checked 2026-09-03 · due a re-check by 2027-09-03 ### Virginia (`virginia`) > the contractor shall be paid at least ninety-five percent of the earned sum when payment is due, with no more than five percent being retained to ensure faithful performance of the contract. All amounts withheld may be included in the final payment. Source: Record: https://referencesource.org/construction-retainage-limits-by-state/virginia/index.md · last checked 2026-09-03 · due a re-check by 2027-09-03 ### Washington (`washington`) > public improvement contracts must provide, and public bodies must reserve, a contract retainage not to exceed five percent of the moneys earned by the contractor as a trust fund for the protection and payment of: (i) The claims of any person arising under the contract Source: Record: https://referencesource.org/construction-retainage-limits-by-state/washington/index.md · last checked 2026-09-03 · due a re-check by 2027-09-03 ### Wisconsin (`wisconsin`) > The retainage shall be an amount equal to not more than 5 percent of the estimate until 50 percent of the work has been completed. At 50 percent completion, further partial payments shall be made in full to the contractor and no additional amounts may be retained unless the architect or engineer certifies that the job is not proceeding satisfactorily, but amounts previously retained shall not be paid to the contractor. Source: Record: https://referencesource.org/construction-retainage-limits-by-state/wisconsin/index.md · last checked 2026-09-03 · due a re-check by 2027-09-03